HIGH COURT
OF SINDH
BENCH AT
SUKKUR.
C.P.No.D- 732 of 2010.
For Katcha
peshi.
-
27.04.2010. Mr.Qurban Ali
Malano advocate for
petitioner.
Mr.Abdul
Sattar Chohan advocate for respondent
No.3 alongwith respondent No.3 Administrator
Taluka Municipal, Administration,
Sukkur.
Mr.Imtiaz Ali Soomro AAG alongwith Ghulam Akbar
Memon District Officer Roads Sukkur and XEN Roads.
-
Administrator
Taluka Municipal Administration Sukkur is present in Court and submits that he
has no knowledge of Mega Project as the same is being handled by Project
Director Mega Project. He however, concedes that he is responsible for all the
administrative problems and to oversee all the development work in Sukkur. He
undertakes that he will consult with the relevant officers and appraise this
Court as to what progress has been made in respect of Mega Project. XEN Public
Health Engineering Department, who is also present in Court submits that as far
as lines of drainage are concerned, they have been laid down and now they will
not dig the road any more so that the District Administrator and Project
Director cargo ahead with a construction work in execution of the Mega Project.
The
Project Director, Administrator Taluka Municipal Administration New Sukkur, and
DCO Sukkur are not present. Office is therefore directed to issue notices
immediately to all the three officers to be present on the next date of hearing
when the Administrator Sukkur is directed to furnish a report as to the
progress of the Project.
For
this purpose, the matter is adjourned to 11.05.2010.
JUDGE
JUDGE
Akber.