ORDER SHEET

IN THE HIGH COURT OF SINDH, KARACHI

C.P. No.D-3970 of 2011

---------------------------------------------------------------------------------------------

Date                     Order with signature(s) of the Judge(s)

---------------------------------------------------------------------------------------------

1)                 For orders on office objection

2)                 For Katcha Peshi

--------------------------------------------

16.05.2013

Mr. Saeed-uz-Zaman, Advocate for Petitioner.

Mr. Sher Muhammad K. Shaikh, Addl: A.G. Sindh.

Dr. Saeed Ahmed Qureshi, Focal Person, Health Department

Mr. Zahid Ali, Superintendent Engineer, Works & Services.

-----------------------------------------------------------

          The instant petition was filed seeking directions against the respondents to pay a sum of Rs.1,614,501/- against the construction work done at Civil Hospital, Karachi. Initially, we were of the view that since the contractual obligations could not be enforced in constitutional jurisdiction, therefore, the petition merits dismissal. However, notices were already issued and comments were received from Works and Services, Health Department and Medical Superintendent, Civil Hospital, Karachi. Each one of the respondents had admitted the claim of the petitioner but stated that due to change in the administration it is to be decided as to whether this amount is to be paid by the Ministry of Works or Ministry of Health, however, none denied the execution of work or payment of the amount. Consequently we directed the Secretary, Works and Services and Secretary Health Department to resolve the issue and submit report and today minutes of the meeting, held between the Secretaries on 15th May 2013, have been placed on record, which read as follows:

“By consent it was decided that since the work executed under directives of Board of Directors of Civil Hospital Karachi and work was executed by an officer of the Works & Services Department posted in Health Department on deputation, hence the summary for release of the required funds will be initiated by the Health Department, to be routed through Works & Services Department and Finance Department and submitted to the competent authority i.e. Chief Minister Sindh, in order to clear the pending liabilities of the petitioner amount to Rs.1,406,316/-“

 

          Perusal of minutes of meeting reflects that the petitioner’s claim for the work done is not disputed but the authority which has to make payment is disputed. Focal person of Health Department says that he will personally ensure that the summary is routed and sanction of the Chief Minister in terms of the minutes of the meeting, reproduced above, is obtained and the payment is made to the petitioner within 20 days. Counsel for the petitioner says that he has no objection even if the payment is made after 30 days but this Court should fix the responsibility of the authority who has to make payment. In terms of the minutes of meeting we, while disposing of this petition, observe that in case the payment is not made to the petitioner within 30 days then the Secretary, Health Department shall make the payment to the petitioner within a week’s time thereafter. It is made clear that in case of noncompliance of this Order, the Secretary Health Department would expose himself to the proceedings for disobedience of the directions of this Court.

           

                                                                                             JUDGE

 