Order Sheet
IN THE HIGH COURT
OF SINDH, BENCH AT SUKKUR
Revision Application No. S – 06 of 2000
[Executive Engineer, Highways Division, Moro & others
v. Nazeer Ahmed & others]
Applicants : Executive Engineer, Highways
Division, Moro & others, through
Mr. Ahmed Ali
Shahani, Assistant Advocate General Sindh.
Respondents : Nemo
Date of hearing : 12-08-2020
Date of order : 27-08-2020
O R D E R
Adnan
Iqbal Chaudhry J. –
F.C. Suit No. 54/1993 filed by the Respondents /
their predecessors (Plaintiffs) for compensation of land consumed in certain
road construction projects, was dismissed by the learned Senior Civil Judge,
Moro; however, in Civil Appeal No. 10/1999, the learned Additional
District Judge, Moro, decreed the suit in part; hence this revision application
by the Applicants (Defendants).
2. It
was the case of the Plaintiffs that in 1972-73, the Government of Sindh
constructed a road from Moro to Mithani (the ‘first road project’) which
utilized part of the Plaintiffs’ ancestral land in Survey No. 373 of Deh Manaheen,
Taluka Moro;[1] that in 1977-78,[2] the
Government constructed a road to village Puran (the ‘second road project’), which
utilized part of the Plaintiffs’ land in Survey Nos. 349, 350 and 351 of Deh
Manaheen; that again in 1993,[3] the
Government utilized the Plaintiffs’ land in Survey Nos. 383, 385 and 782 of Deh
Manaheen to construct the Nather Ditta road[4] (the
‘third road project’). It was contended that time and again the Plaintiffs
approached the Executive Engineer Highways, Moro, for compensation of said land,
but in vain; hence the prayer for damages @ Rs.100,000/- per acre.
3. Officers
of the Highways Division were arrayed as Defendants 1 to 3. The Land
Acquisition Officer was arrayed as Defendant No. 4. The Province of Sindh was
arrayed as Defendant No. 5 although it was wrongly sued through the Deputy
Commissioner Naushahro Feroze. A written statement was filed by the Executive
Engineer, Highways Division, Moro. The suit proceeded ex-parte
against the Land Acquisition Officer and the Province.
4. It
was the case of the Highways Division that while the said three road projects
had been undertaken by them, the land for the same had been duly acquired by
the Government under the Land Acquisition Act, 1894; that for acquiring the
land for the first and second road projects in the year 1972-73 and 1977-78
respectively, the Highways Division had made the prescribed payment to the
Acquisition Office B&R, Hyderabad, who in turn had released compensation to
the affected khatedars, albeit in view of a higher rate subsequently
recommended by the Deputy Commissioner Nawabshah, the matter with regards to
additional compensation was still pending; that the Plaintiffs had never
approached the Land Acquisition Officer for compensation; and that the third
road project was constructed under a Senator Scheme sponsored under the
Tameer-e-Watan Program. It was further contended that Survey No. 373 in
Deh Manaheen claimed by the Plaintiffs, had never been utilized in the road
projects.
5. By
judgment and decree dated 12-11-1998, the trial court dismissed the suit
holding that the Plaintiffs had failed to prove that in the years 1972-73 and
1977-78 they were owners of the Survey Numbers claimed by them; that village Form-XV
produced by the Plaintiffs was not reliable evidence of ownership of the land
in question as the same was issued in the year 1980; and that in any case, the remedy
of the Plaintiffs for compensation was before the authority/forum designated under
the Land Acquisition Act, 1894.
6. On
the appeal of the Plaintiffs (Respondents herein), the appellate court passed
judgment for the Plaintiffs holding that village Form-XV was sufficient
evidence of the Plaintiffs’ ownership of Survey Nos. 349, 350 and 351; that the
evidence showed that land in Survey Nos. 349, 350 and 351 had been acquired by
the Government for constructing a road to village Puran (second road project)
for which the Plaintiffs were not compensated; and by a preliminary decree
dated 19-05-1999, the appellate court proceeded to appoint a commissioner to
determine the rate of land and the area acquired. On receipt of the
commissioner’s report, the appellate court then passed a final decree dated 23-10-1999
awarding compensation to the Plaintiffs @ Rs.100,000/- per acre to the extent
of 4-07 acres of land in Survey Nos. 349, 350 and 351 of Deh Manaheen, Taluka
Moro, i.e. a sum of Rs.417,500/-.
7. Thus,
while the trial court held that the Plaintiffs had not been able to prove
ownership of any part of the land claimed in the suit, the appellate court held
that the Plaintiffs had been able to prove ownership of least of Survey Nos. 349,
350 and 351. The Plaintiffs did not appeal the denial of relief for the other
Survey Numbers. Therefore, it is only Survey Nos. 349, 350 and 351 of Deh
Manaheen that are relevant to this revision.
8. The
learned AAG Sindh submitted that suit for compensation for land acquired in
1972-73 and 1977-78 was time-barred; that the appellate court mis-read the
evidence in holding that the Plaintiffs had proved ownership to the land in
question; and that, since the land had been acquired under the Land Acquisition
Act, 1894, and since the Plaintiffs had not approached the authority/forum
under the said Act for compensation, the civil court could not have exercised general
jurisdiction to decide the question of compensation as so held in Abdul
Manan v. Chairman WAPDA (1990 CLC 1377).
9. Heard
the learned AAG Sindh and perused the record.
10. In
their objections to this revision, the Respondents (Plaintiffs) have taken the
plea that the revision is time-barred. I advert to that objection first.
The preliminary decree passed
by the appellate court is dated 19-05-1999. The final decree is dated
23-10-1999. The revision is directed against both. From the final decree, this
revision application filed on 20-01-2000, on the 89th day, is within
the limitation of 90 days. However, if separate limitation is computed for the
preliminary decree, then to that extent the revision is delayed by 156 days. But
then, section 97 CPC which precludes a party from disputing the correctness of a
preliminary decree in an appeal from the final decree when no appeal was
preferred from the preliminary decree, does not put the same restriction on a
revision application. Rather, under section 115 CPC, a revision is against a
‘case decided’. However, that is not to say that a revision application can
never be filed against a preliminary decree before the passing of a final
decree, inasmuch as the terms of a preliminary decree may well be a ‘case
decided’ within the meaning of section 115 CPC.[5] Nevertheless, in my view, where the question
is to the very jurisdiction of the sub-ordinate court to decide the case, such
question remains open in a revision from the final decree even though no
revision application had been preferred from the preliminary decree.[6]
Thus, this revision is within
limitation.
11. I
now advert to the grounds of the revision. It appears that to hold that the
Plaintiffs had proved ownership to Survey Nos. 349, 350 and 352 of Deh
Manaheen, the learned appellate court relied on village Form-XV produced by the
Plaintiffs. Suffice to observe that in the absence of any document / entry to
show title of the Plaintiffs’ predecessors through whom the Plaintiffs claimed
to have inherited Survey Nos. 349, 350 and 352, village Form-XV on its own was hardly
proof of ownership to the said land.
12. Be
that as it may, like the trial court the appellate court too found that the
land claimed by the Plaintiffs in Survey Nos. 349, 350 and 351 had in fact been
acquired by the Government under the Land Acquisition Act, 1894 for the public
purpose of constructing a road. The learned AAG Sindh has also filed a copy of notice
dated 27‑12‑1994 issued under section 9 of the Land Acquisition
Act, and the award dated 18-05-1995 made under section 11 thereof in respect of
land acquired for constructing the road to village Puran, Taluka Moro, which included
the subject Survey Nos. 349, 350 and 351. From the award it appears that while
the said land was occupied by the Government in the year 1986, the notice
inviting claims for compensation pursuant to section 9 of the Land Acquisition
Act was delayed until 1994, after the suit had been filed in 1993. However,
even after the suit, when compensation proceedings under the Land Acquisition
Act were disclosed in the written statement of the Highways Division, the
Plaintiffs did not file a claim for compensation before the Collector pursuant
to section 9 of the Land Acquisition Act, nor did they move under section 18
thereof for making a Reference against the award to the court designated for
such purpose. The acquisition proceedings remained unchallenged. Therefore, the
suit of the Plaintiffs cannot be said to be one envisaged under section 52 of
the Land Acquisition Act to question anything done in pursuance of the said Act.
13. In
the circumstances of the case, given the failure of the Plaintiffs to invoke the
special jurisdiction of the designated court under section 18 of the Land
Acquisition Act, 1894, there was an implied bar, as
contemplated under section 9 CPC, to the general / plenary jurisdiction of the civil
court to decide the Plaintiffs’ suit for compensation. Such implied bar could
only be circumvented if the Plaintiffs demonstrated that the case attracted one
of the established exceptions to the ouster of the plenary jurisdiction of a
civil court[7],
which, as already noted, was not the case set-up by the Plaintiffs.
14. For the foregoing reasons, the decree
passed by the appellate court awarding compensation for land acquired under the
Land Acquisition Act, 1894, was without jurisdiction. Accordingly, this revision application is allowed; the
judgment, the preliminary decree and the final decree passed by the appellate
court in Civil Appeal No. 10/1999 are set-aside; and the judgment and
decree passed by the trial court dismissing F.C. Suit No. 54/1993 is restored.
J U D G E
[1] Plaint and deposition of PW-1, Nazeer Ahmed.
[2] Cross-examination
of PW-1.
[3] Cross-examination of PW-1.
[4] Deposition of PW-1.
[5] For what is a
‘case decided’ within the meaning of section 115 CPC, see Anjum Chemical
Storage (Pvt.) Ltd. v. Chenab Ltd. Nishatabad (2016 SCMR 177), and Nestle
Milkpak Ltd. v. Classic Needs Pakistan (Pvt.) Ltd. (2006 SCMR 21).
[6] In Hafeez Ahmed v. Civil Judge, Lahore (PLD 2012 SC 400),
the Supreme Court held that if the High Court or the District Court, as the
case may be, is of the view that the case decided by the sub-ordinate suffers
from a jurisdictional error and must be corrected, the fact that the revision
application is beyond the prescribed time is no impediment, as the Court can
nonetheless exercise suo moto powers under section 115 CPC to correct
the error.
[7] These exceptions
are reiterated in Searle IV Solution
(Pvt.) Ltd. v. Federation of Pakistan (2018 SCMR 1444).