ORDER SHEET
IN THE HIGH COURT OF SINDH,
KARACHI
C.P. No.D-6022 of 2018
__________________________________________________________________
Dated: Order with signature of
Judge(s)
__________________________________________________________________
1. For order on Misc. No.26067/2018
2. For order on Misc. No.26068/2018
3. For order on Misc. No.26069/2018
4. For order on Misc. No.26070/2018
5. For hearing of main case.
----------------------------------------------------
17.08.2018
Mr. Irfan Aziz, advocate for the petitioner.
_____________
1) Urgency
granted.
2) Exemption
granted subject to all just exceptions.
3&4) Learned counsel for the petitioner contends that the
petitioner is owner of Flat No.4, First Floor, Habib Mansion, Gali No.9, on Plot No.AM-1/23, Burns Road, Karachi. Learned
counsel further contends that respondents No.4, 5 and
6 despite sealing order issued by the respondents No.2
and 3 (copy of the same is available as annexure “B” at page-59 with MoP) are trying to raise constructions of a hotel for
commercial basis illegally and unauthorizedly.
Petitioner has lodged complaints to different authorities for such illegal
construction, which are available as annexures “A/1 and A/2” with MoP but till this date no action has been taken to stop the
illegal construction on the subject plot/building.
Issue notice to the
respondents for 04.09.2018. In the
meantime, respondents No.2 and 3 are directed to take
appropriate legal action against the respondents No.4,
5 and 6 and other persons who are raising illegal construction on the subject
plot/building contrary to approved building plan and Karachi Buildings and Town
Planning Regulations, 2002. Respondents No.2 and 3
are further directed to take concrete steps to restrain the respondents No.4, 5 and 6 and other persons from raising illegal
construction on the subject plot/property and submit comprehensive compliance
report to this Court on or before next date of hearing. Respondent No.7 is directed to provide requisite police force to the
officials of the SBCA at the time of taking action to
stop illegal construction on the subject plot/property as and when required.
Copy of this order be
communicated to the respondents No.2 and 3 in ordinary
course and through facsimile for information and compliance.
JUDGE
JUDGE