C.P.No.D-1347 of
2009
For Katcha Peshi
25.11.2015
Mr. Manzoor Hussain Larik Advocate along with
petitioner.
Mr. Shaharyar Awan, Assistant Advocate
General a/w Mir Ahsan Ali Talpur, XEN, Provl. Highway
Division, Naushahro Feroze.
................
Pursuant
to Court notice, Mir Ahsan Ali Talpur, XEN has shown
appearance and has filed comments, which are taken on record and copy supplied
to learned counsel for the petitioner. XEN submits that the scheme relating to
construction of road from New Indus Bridge @ Razi Dero via Kandiaro Road has
once again been dropped, as funds have not been released from Finance
Department, whereas, necessary letters have been written to the PSDP to include
the aforesaid scheme in the next financial year i.e. 2016-17.
Learned
counsel for the petitioner submits that the respondents may be directed to
expedite the matter so that already approved scheme, work on which started few
years back and 05 KM road was constructed, however, thereafter, work on such
scheme has been stopped. It has been prayed that scheme shall be completed
within shortest possible time so that the residents of the area and other
persons of the locality may utilize such road, which will also be helpful in
the development of the area.
Accordingly,
instant petition is being disposed of with directions to the respondents to
ensure that already approved scheme, which according to learned counsel for the
petitioner, was commenced and has been suspended on account of non-allocation
of funds by the Finance Department, Government of Sindh, shall be resumed
within a reasonable time to avoid revision of such scheme, which increases its
cost and there is loss of public exchequer. It is expected that Services and
Works Department shall ensure that all schemes relating to public works shall
be completed as per original plan, without sending the same to revision on
account of non-allocation of funds, within the prescribed time so that there
shall be no loss of public exchequer, whereas, all the public schemes shall be
completed within stipulated time as per original cost, which will not only
eliminate the corruption but will also facilitate the public at large, who are the
ultimate beneficiaries of such public scheme. The respondents will further
ensure that the budget already sanctioned for any public scheme shall be
utilized for such public scheme within the given time frame and shall not lapse,
so that the scheme may not be sent for revision. Let copy of this order may be
sent to the Chief Engineers, Sukkur Region and Hyderabad Region for their
information and compliance.
Petition stands
disposed of in the above terms.
JUDGE
JUDGE
N.M.